On February 28, 2007, the City of Fremont opened the new bids for the main contract. The results were as follows:
Contractor
DeSilva Gates – Brosamer (JV)
RGW Construction, Inc.
FCI Constructors, Inc.
Base Bid Total
$48,151,286
$49,286,444*
$53,470,541
Rank
1
2
3
* Mathematically corrected: RGW Construction, Inc.
Engineer's Estimate $49,550,000
The anticipated award date for the main contract is late March 2007 with a Notice to Proceed in mid to late April 2007. Construction activities on the main contract are expected to begin in June 2007.